    24th - 28th February - Week 14

    Scroll down for our most recent update.


    Hardcore is now filling the school, leaving a gap at the top to allow for the concrete floor - it is hoped to cast the floor during the first week of March.

    Holes are being drilled in the blockwork to take the service pipes (left). We have to decide on the brick colour, so a small section has been built to give an idea of the final, finished look. Are these bricks too black/grey (right) - and therefore a little 'dead'? We were looking for a blue brick finish and these don't really fit the bill!





    Wednesday saw a return to rather wet, dull weather. In preparation for the casting of the floor slab, iron mesh has been delivered. This will give added strength to the floor, when the concrete is poured next week.


    Day One | Week 1 - days 2-6 | Week 2 | Week 3 | Weeks 4, 5 and 6 | Week 7 | Week 8 | Week 9 | Week 10 | Week 11 | Week 12 | Week 13 | Week 14 | Week 15 | Week 16 | Week 17 | Week 18 | Week 19 | Week 20 | Weeks 21 and 22 | Week 23 | Week 24 | Week 25 | Week 26 | Week 27 | Week 28 | Week 29 | Week 30 - 32 | Weeks 33 - 36 | Weeks 37 - 39 | Weeks 40 - 42 | Weeks 43 - 44 | Weeks 45-46 | Weeks 47 - 48 | Weeks 49 - 50 | Weeks 51-52 | One Year On!

    Home | See the plans and meet some of the team