    19th - 23rdMay - Week 26

    Yes, the floor of the first floor has been laid - I sneaked up the stairs and took a few photos from above! This one shows the hall.

    The shorter side of the hall has reached roof level. Block laying is very weather dependant, and a few days are being lost due to the rain.

    The next stage was to cast eight concrete pillars. These will stand in the courtyard and give support to our new Science / Art room.

     

     

    Steel is now being fitted to the top of these pillars. The floor of the Science / Art Room
    will then be positioned. Once the floor of First Floor is completed, block laying of the next
    storey will commence. All the internal blockwork of the Ground Floor (toilet areas, kitchen
    to the hall, etc.) has been completed.

    We are now very seriously looking at furniture for all rooms and will be getting quotes
    for a new suite of computers shortly.



     

    Day One | Week 1 - days 2-6 | Week 2 | Week 3 | Weeks 4, 5 and 6 | Week 7 | Week 8 | Week 9 | Week 10 | Week 11 | Week 12 | Week 13 | Week 14 | Week 15 | Week 16 | Week 17 | Week 18 | Week 19 | Week 20 | Weeks 21 and 22 | Week 23 | Week 24 | Week 25 | Week 26 | Week 27 | Week 28 | Week 29 | Week 30 - 32 | Weeks 33 - 36 | Weeks 37 - 39 | Weeks 40 - 42 | Weeks 43 - 44 | Weeks 45-46 | Weeks 47 - 48 | Weeks 49 - 50 | Weeks 51-52 | One Year On!