18th August - 5th September - Weeks 40 - 42
With the terrific weather in August, very few days have been lost and therefore everything is still on target for a Hallowe'en move! Site meetings continue every second Friday and our minds are currently taken up with furniture and computer networking. We also need to decide on the final height of the fixed stage in the hall at this point.
The electricians are busily wiring the building ...
... while the plumbers are - well - plumbing!
The photo on the right by the way, is the staff shower - building regulations require that we have one.
Windows have been delivered and started installation on Monday
25th August. The photo on the right is the staffroom. The little room leading
from the staffroom - just visible in the photo - will be a staff workroom.
Day One | Week 1 - days 2-6 | Week 2 | Week 3 | Weeks 4, 5 and 6 | Week 7 | Week 8 | Week 9 | Week 10 | Week 11 | Week 12 | Week 13 | Week 14 | Week 15 | Week 16 | Week 17 | Week 18 | Week 19 | Week 20 | Weeks 21 and 22 | Week 23 | Week 24 | Week 25 | Week 26 | Week 27 | Week 28 | Week 29 | Weeks 30 - 32 | Weeks 33 - 36 | Weeks 37 - 39 | Weeks 40 - 42 | Weeks 45-46 | Weeks 47 - 48 | Weeks 49 - 50 | Weeks 51-52 | One Year On!/font>