20th - 31th October - Weeks 49 - 50
The screen around the courtyard is now in the process of erection and it looks absolutely terrific.
There's still a little old foundation left to remove! |
The outside has now been fully plastered and practically painted. |
This is typical of the door frame entering each classroom. |
Finally, a look at the hall, as some electrical work is being completed. Wouldn't I love one of those gadgets to clean our windows at home!!!
All the windows of the school (manufactured by Rationel) are now in place and judging by our site meeting on Friday 18th October, we are still on schedule to move in during the weekend of 14th November.
Floor covering for all wet areas and corridors is starting on Monday 20th October. Classroom carpeting starts later.
Furniture
has been ordered and will arrive during the first week on November - just after
half term. As mentioned earlier, the lift has been manufactured in Ennis and
will very shortly be called on site. It will be delivered in two parts - and
will hopefully fit the hole left for it!
Day One | Week 1 - days 2-6 | Week 2 | Week 3 | Weeks 4, 5 and 6 | Week 7 | Week 8 | Week 9 | Week 10 | Week 11 | Week 12 | Week 13 | Week 14 | Week 15 | Week 16 | Week 17 | Week 18 | Week 19 | Week 20 | Weeks 21 and 22 | Week 23 | Week 24 | Week 25 | Week 26 | Week 27 | Week 28 | Week 29 | Weeks 30 - 32 | Weeks 33 - 36 | Weeks 37 - 39 | Weeks 40 - 42 | Weeks 43 - 44 | Weeks 45 - 46 | Weeks 47 - 48 | Weeks 49 - 50 | Weeks 51-52 | One Year On!