22nd September - 3rd October - Weeks 45 - 46
Time has come to choose colours for floor covering. Each classroom will be carpeted, leaving a section of non-slip marmoleum in the wet areas.
Liz, Richard Hannay and I met in the office
and started going through the various options available. Contractors will
arrive in a matter of weeks to put these down. The Board of Management had
the chance to view our ideas and a final choice was made.
The interior will be painted an off-white colour and once again, contractors will shortly be arriving to start this.
Plasterers
have arrived and have been busy working on the exterior of the building. This
will be painted - though the
colour is uncertain yet. Around the central courtyard will also be plastered.
A wooden surround is now framing the
Science/Art Room window and in time a copper front piece will be mounted to
give the front of the school a trendy look!
The ceilings are going in this week.
The picture
on the left is where the lift will be positioned. The
lift has been manufactured and is waiting to be called on site.
I thought you would like to get a look at one of our site meetings. These
take place every fortnight, usually on a Friday.
Finally,
it is looking a little unlikely that we will move into the new building after
half term, as we had planned. It now appears that mid November is more realistic.
We'll
keep you posted!
Day One | Week 1 - days 2-6 | Week 2 | Week 3 | Weeks 4, 5 and 6 | Week 7 | Week 8 | Week 9 | Week 10 | Week 11 | Week 12 | Week 13 | Week 14 | Week 15 | Week 16 | Week 17 | Week 18 | Week 19 | Week 20 | Weeks 21 and 22 | Week 23 | Week 24 | Week 25 | Week 26 | Week 27 | Week 28 | Week 29 | Weeks 30 - 32 | Weeks 33 - 36 | Weeks 37 - 39 | Weeks 40 - 42 | Weeks 43-44 | Weeks 45-46 | Weeks 47 - 48 | Weeks 49 - 50 | Weeks 51-52 | One Year On!