Home | Our Parish | Our New Building | Our Classes | Calendar | Photo Gallery | Children's Pages

    3rd - 7th March - Week 15


    There's not a lot happening on site at the moment. Deliveries of the steel for the floor are awaited. When they arrive, the floor slab will be cast and the brick layers will return - hopefully just after St. Patrick's Day!

    Meanwhile, meet First Class!! They had the opportunity during this quiet time to see what has been going on behind the hoarding. Other classes will get the same chance during the week.




    On Wednesday, it was the turn of Second Class. They were full of questions and enjoyed seeing the progress that is being made. And indeed, things are pressing on ...



    ... as you can see from these photos. The steel has been delivered and we can now see the final height of the hall. These were bolted and concreted directly to the foundations. Because the steel supports were a little late arriving, the casting of the floor slab has been deferred to next week.




    The service pipes are being fixed into place in readiness for the pouring of the floor.


    Day One | Week 1 - days 2-6 | Week 2 | Week 3 | Weeks 4, 5 and 6 | Week 7 | Week 8 | Week 9 | Week 10 | Week 11 | Week 12 | Week 13 | Week 14 | Week 15 | Week 16 | Week 17 | Week 18 | Week 19 | Week 20 | Weeks 21 and 22 | Week 23 | Week 24 | Week 25 | Week 26 | Week 27 | Week 28 | Week 29 | Week 30 - 32 | Weeks 33 - 36 | Weeks 37 - 39 | Weeks 40 - 42 | Weeks 43 - 44 | Weeks 45-46 | Weeks 47 - 48 | Weeks 49 - 50 | Weeks 51-52 | One Year On!/font>

    Home | See the plans and meet some of the team